Iberdrola and 50Hertz sign construction agreement for Baltic Eagle offshore substation
Renewable Energy World
MAY 20, 2021
When the Baltic Eagle wind farm is connected to the grid, the wind turbines will deliver electricity via the inter-array cables to the offshore substation where it will then be transformed from 66 kV to 220 kV and transmitted via two high voltage subsea cables across 90 km to the landing point at Lubmin.