Calpine to bring majority of 680MW California BESS online this summer

LinkedIn
Twitter
Reddit
Facebook
Email

Gas and geothermal plant operator Calpine Corporation will bring 510MW of its 680MW capacity battery energy storage system (BESS) project in California online in summer 2024, with BYD battery units.

The 510MW phase one of the Nova Power Bank will be complete this summer, with another 110MW coming online in autumn and the final 60MW in 2025, Calpine said this week.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

It is the first time Calpine has officially announced the Nova project, with Energy-Storage.news reporting on it using various sources in January this year (Premium access), when White & Case announced a US$1 billion-plus financing round for it.

The 43-acre project is on the former site of Calpine’s Inland Empire legacy power plant, which it decommissioned in late 2022.

It didn’t reveal the capacity of the project but said that it could power 680,000 homes for four hours, implying it has a 4-hour duration, as the vast majority of California projects do. That would make it 2,720MWh, slightly smaller than the two largest operational BESS projects in the world, Moss Landing (3,000MWh) and Edwards & Sanborn (3,272MWh), both also in California.

It said that utilities Southern California Edison (SCE), Peninsula Clean Energy, and San Diego Gas & Electric will use the electricity from the project, presumably through Resource Adequacy, grid operator CAISO’s means of ensuring there is enough power to supply demand with a reserve margin.

Based on previous documents from the California Public Utilities Commission (CPUC), SCE will specifically contract for the 110MW coming online in fall.

Calpine Corporation operates natural gas and geothermal resources across the US with 78 plants. It already has a 80MW BESS in operation in California, called Santa Ana, and two under construction in addition to Nova: the 25MW West Ford Flat BESS and the 13MW Bear Canyon BESS. The company claims to have 2,000MW of BESS in development in total.

22 October 2024
New York, USA
Returning for its 11th edition, Solar and Storage Finance USA Summit remains the annual event where decision-makers at the forefront of solar and storage projects across the United States and capital converge. Featuring the most active solar and storage transactors, join us for a packed two-days of deal-making, learning and networking.
18 March 2025
Austin, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2025!

Read Next

June 6, 2024
Another edition of news in brief from around the world in energy storage, with Powin, ESS Inc and New Zealand’s Counties Energy.
June 6, 2024
While short-duration BESS has flourished in Ireland, a ‘policy vacuum’ threatens the long-duration energy storage (LDES) rollout required for its renewables goals, research firm Cornwall Insights said.
June 6, 2024
Developer and IPP Leeward Renewable Energy and California utility PG&E have agreed a long-term resource adequacy (RA) agreement for a large-scale, PV co-located BESS in Arizona.
June 6, 2024
Developer and EPC Eco Stor will start building another 103.5MW/238MWh BESS project in Germany in November this year.
June 6, 2024
Prevalon, the US battery storage solutions provider spun out of Mitsubishi Power Americas, intends to deploy 2.5GWh of systems using Rept Battero’s technologies this year.

Most Popular

Email Newsletter