Hawaiian Electric starts negotations on 2.1GWh of hybrid storage projects for 2026-33 delivery

LinkedIn
Twitter
Reddit
Facebook
Email

Hawaii’s main utility Hawaiian Electric has entered into contract negotiations with the developers of 15 renewable energy projects, including solar, wind and a combined 2.1GWh of energy storage.

The projects are spread across the islands of Oahu, Hawaii Island and Maui and will combine renewable energy generation including biofuel-powered generators and energy storage to ensure firm generation.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The contacts entered into after negotiations are expected to cover around 517MW of variable generation, 654MW of firm generation and 2.1GWh of energy storage, with completion dates mandated for between 2026 and 2033.

Developers include Ameresco, Clearway – both having worked on co-located projects in Hawaii previously – Longroad Development, AES and Pacific Current and Terraform, which added a storage facility to a small wind farm there a few years ago. AES is the US-listed energy firm with a global presence, one of the founding companies of battery energy storage integrator Fluence.

Seven will be on the island of Oahu, four on Hawaii Island and four on Maui, totalling 990MWh, 320MWh and 834MWh of energy storage capacity respectively. See a full table of the projects below.

Project nameIslandDeveloperTechnologySize
Puuloa EnergyOahuAmerescoInternal combustion engines (biofuel)99MW
Puuloa SolarOahuAmerescoSolar + BESS6MW + BESS
Base ProposalOahuKalaeloa Partners LPCombustion turbine (biofuel)208MW
Waiau RepowerOahuHawaiian ElectricCombustion turbine (biofuel)253MW
Mahi Solar and StorageOahuLongroad DevelopmentSolar + BESS120MW + BESS
Makana LaOahuClearway Energy GroupSolar + BESS80MW + BESS
Par Hawaii Renewable Combined Heat & PowerOahuPar Hawaii RefiningCombined heat & power (biofuel)33.9MW
Kuihelani Phase 2 SolarMauiAES Corp.Solar + BESS40MW + BESS
Puu Hao SolarMauiAES Corp.Solar + BESS20MW + BESS
Kaheawa Wind 1MauiTerraform USWind30MW
Pulehu Solar & StorageMauiLongroad EnergySolar + BESS20MW + BESS
Keamuku SolarHawaii IslandAES Corp.Solar + BESS86MW + BESS
Puako SolarHawaii IslandClearway Energy GroupSolar + BESS60MW + BESS
Kaiwiki SolarHawaii IslandClearway Energy GroupSolar + BESS55MW + BESS
Hamakua Firm Renewable EnergyHawaii IslandPacific CurrentCombined Cycle (biofuel) + BESS60MW + BESS

“These projects will help move Hawaii closer to its clean energy goals, while adding critical grid reliability with firm renewable energy,” said Rebecca Dayhuff Matsushima, vice-president of Resource Procurement for Hawaiian Electric. “Adding energy storage and generation from firm renewables to our portfolio will make it easier for Hawaiian Electric to retire older, less flexible fossil fuel-fired plants.”

The two combustion engine projects on Oahu and the Hamakua project on Hawaii Island are transforming facilities that currently burn imported fossil fuels into biofuel-based ones.

Once the contracts between Hawaiian Electric and the project finalised they will be submitted to the Public Utilities Commission of Hawaii for review and approval.

The projects need to contribute US$3,000 per MW of installed power in the form of community benefits.

Energy-Storage.news’ publisher Solar Media will host the 5th Energy Storage Summit USA, 19-20 March 2024 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

21 May 2024
Napa, USA
PV Tech has been running PV ModuleTech Conferences since 2017. PV ModuleTech USA, on 21-22 May 2024, will be our third PV ModulelTech conference dedicated to the U.S. utility scale solar sector. The event will gather the key stakeholders from solar developers, solar asset owners and investors, PV manufacturing, policy-making and and all interested downstream channels and third-party entities. The goal is simple: to map out the PV module supply channels to the U.S. out to 2025 and beyond.
22 May 2024
London, UK
At the time of writing, Europe had had its most successful year in terms of Power Purchase Agreements (PPAs) with a record 7.8GW of renewable energy contracts signed. As we gather in May 2024 for the third edition of the Renewable Energy Revenues Summit, the energy landscape continues to evolve rapidly, influenced by the beating drum of climate change, volatility around power prices and the need to decarbonise power procurement as well as generation.
8 October 2024
San Francisco Bay Area, USA
PV Tech has been running an annual PV CellTech Conference since 2016. PV CellTech USA, on 8-9 October 2024 is our second PV CellTech conference dedicated to the U.S. manufacturing sector. The event in 2023 was a sell out success and 2024 will once again gather the key stakeholders from PV manufacturing, equipment/materials, policy-making and strategy, capital equipment investment and all interested downstream channels and third-party entities. The goal is simple: to map out PV manufacturing in the U.S. out to 2030 and beyond.
22 October 2024
New York, USA
Returning for its 11th edition, Solar and Storage Finance USA Summit remains the annual event where decision-makers at the forefront of solar and storage projects across the United States and capital converge. Featuring the most active solar and storage transactors, join us for a packed two-days of deal-making, learning and networking.

Read Next

May 7, 2024
Storage developer and operator Lightshift Energy will deploy numerous distributed BESS projects totalling 50MW for various utilities via the Massachusetts Municipal Wholesale Electric Company (MMWEC).
May 3, 2024
Optimiser Habitat Energy has secured a deal with UBS Asset Management to handle the energy market activity of four BESS projects totalling 730MW in ERCOT, Texas.
May 2, 2024
Developer energyRe has secured US$240 mllion from Bank of America to fund the 108MWdc/198MWh Lone Star solar-plus-storage project in South Carolina, US.
May 1, 2024
G7 nations have agreed a new global energy storage target of 1500GW by 2030, a six-fold increase from today’s levels.
April 30, 2024
Developers Agilitas Energy and On.Energy have raised a total US$125 million in debt financing towards solar, energy storage and hybrid solar-plus-storage projects in the US.